Roof Update

Dear Club Members,

Balfour Beatty are continuing at a brisk pace with the roof repairs and this is currently still on schedule, here are a few updates and milestones from Everyone Active:

  1. Building will become air tight late September;
  2. Pontoons to be removed from both pools in late September;
  3. Dive team booked for early October;
  4. Work on the internal Glulam beams has been completed;
  5. Works on the outer roof continues with a number of roof layers still to be fitted as part on the scheduled works;
  6. Gantry removal at high level commenced with expected completion of mid-September;
  7. NEW LED Lighting system commencing in the area above the pool in early September and scheduled to be completed by mid-October;
  8. Pool plant, water heating system and air handling units to be serviced and switched back on full from mid to end of September;
  9. Microbiological testing to be increase in late-September (has continued during works).

I have also been provided with some pictures below – any further updates will be shared once available.

 

Kindest Regards

Linda

Chair

COSASC